Every office move has a hierarchy of panic, and IT sits at the top for one reason: lead times. Furniture arrives in days, but a leased line takes 30-90 working days, landlord permissions take weeks, and cabling can only happen once you have access. The businesses that walk in on Monday with everything working are the ones that started the connectivity clock the day the lease was agreed. This is the order of operations.
Twelve weeks out: order connectivity before anything else
The day the new address is certain, check availability and order the main circuit — a leased line's 30-90 working day lead time is the critical path of the entire move. Ask whether the building already has fibre and which carriers are on-net; an on-net building can shave weeks off.
Order the wayleave conversation (landlord permission for any fibre works) in the same breath — it's the single most common cause of delay and it costs nothing to start early.
Ten weeks out: design before you drill
Get a floor plan and mark every desk, printer, meeting room, door-entry point and CCTV camera. That plan drives the structured cabling specification — how many points, where the comms cabinet lives, what Wi-Fi coverage needs to reach (including the kitchen, where half your video calls will secretly happen).
Cable once, properly: Cat6a for new installs, tidy containment, a labelled patch panel and a cabinet with power, cooling and room to grow. Retro-fitting points after the furniture arrives costs three times as much.
Six weeks out: phones, numbers and the paper trail
If you're still on an on-premise phone system, a move is the natural moment to go cloud — the number porting happens once and the system stops being tied to an address forever. Either way, plan number routing for move week: numbers are cloud-routed, so calls follow you, not the building.
Paper trail in parallel: serve notice on circuits staying behind (mind the 30-90 day notice clauses), inventory every service billed to the old address, and book any lift access and out-of-hours slots the building needs for move weekend.
Two weeks out: prove the new site before the move
By now the new circuit should be live. Test it properly — throughput, latency, VoIP quality — and stand up the network: firewall, switches, Wi-Fi, printers, door entry. The goal is that the new office is a working office with no people in it.
Prepare a temporary fallback regardless: a 4G/5G router held in reserve covers you if anything slips, and afterwards it becomes your permanent backup connection — the move pays for the resilience.
Move weekend: a checklist, not a drama
With the groundwork done, the weekend is mechanical:
- Friday: users shut down and label kit; servers/NAS powered down last and transported insured
- Saturday: desks patched to the labelled plan; core services up; test sheet walked — internet, Wi-Fi, phones, printers, door entry, CCTV, card machines
- Sunday: remote-work test from outside the network; monitoring re-pointed at the new site; snag list written
- Monday 08:00: an engineer on the floor for the first morning — the difference between snags and chaos
The one decision that de-stresses everything
Appoint a single owner for the IT move — internal or external — with the authority to chase carriers, landlords and suppliers weekly. Moves fail in the gaps between vendors, not inside any one of them.
This is a service we run end to end for managed IT clients: connectivity ordering, cabling, phones, the weekend itself and the Monday morning. If a move is on your horizon, talk to us before you sign the lease — building connectivity is worth checking before you commit to an address.