Relocating an office is one of the few projects where IT can quietly derail the whole move. Furniture arrives in a day; a business-grade internet circuit can take months. The good news is that a smooth relocation is almost entirely down to planning and lead times — not luck. This guide sets out a practical, London-focused checklist to move office without losing internet access, phone service or the ability to work on day one.
Start with the one date that matters: your connectivity lead time
The single biggest risk in any office move is internet connectivity, because it is the item with the longest and least flexible lead time. A standard broadband line may be provisioned in days, but a business-grade circuit such as a leased line typically takes several weeks to a few months — longer if new fibre needs to be dug to the building or landlord permissions (wayleaves) are required.
Because of this, connectivity should be ordered the moment your new address is confirmed, ideally before you sign contracts on furniture or removals. Ask the provider to run a survey on the exact postcode and, crucially, the exact unit — fibre availability can differ between floors and suites in the same London building.
If you want zero downtime, plan to have the new circuit live and tested while you are still occupying the old premises. That overlap costs a little in double rent or dual line rental, but it is far cheaper than a team unable to work. Our leased lines and dedicated internet access pages explain realistic install timescales.
Build a realistic relocation timeline
Work backwards from your move date and map each dependency. Cabling can't be tested until it's installed; the network can't go live until cabling and the internet circuit are ready; phones and devices can't be configured until the network is up. Sequence matters.
A typical London office relocation benefits from a 10–12 week runway, though larger or multi-site moves need more. Circuits and any building works should be the first things booked, with desk-level tasks slotted in during the final fortnight.
- 10–12 weeks out: confirm address, survey and order internet circuits and phone lines
- 8 weeks out: plan floor layout, desk positions and structured cabling requirements
- 6 weeks out: schedule cabling install, network hardware and Wi-Fi survey
- 4 weeks out: order or reconfigure phone system, number porting and mobiles
- 2 weeks out: build and test the network, configure firewall and Wi-Fi
- Move weekend: physically relocate kit, verify connectivity, test phones
- Week after: snag list, decommission old lines once new site is stable
Don't assume the cabling is fit for purpose
Many London offices, especially older conversions and serviced units, have cabling that is undocumented, damaged or below the standard your equipment needs. Never assume existing points work or that they reach the desks in your new layout. A quick survey against your floor plan will reveal how many data outlets you actually need and where.
Structured cabling should be installed and tested before your network hardware arrives, with each outlet labelled back to the comms room patch panel. This makes fault-finding on move day dramatically faster and avoids the classic scenario of a live team sharing a single working socket.
If your new site needs new runs, a cabinet or a tidy comms room, plan it early — engineers get booked up. See our structured data cabling service for how outlets, patch panels and testing fit together.
Keep your phones working: numbers, porting and cloud systems
Phone continuity worries businesses more than almost anything, because customers judge you on a ringing line. If you still run traditional lines, the number porting process to a new provider or system takes time and must be scheduled — you cannot rush it on the day.
Moving to a cloud-based phone system removes most of the pain, because your numbers and extensions travel with you over the internet regardless of physical address. A cloud hosted PBX or a Teams phone system means staff can keep taking calls from home, the old office or a mobile during the transition.
Confirm which numbers you must keep, request porting in writing with realistic dates, and never cancel your old service until the new one is proven. Losing a main business number is one of the hardest mistakes to reverse.
Have a backup plan for the gap
Even well-planned moves hit surprises: a delayed circuit, a wayleave stuck with the landlord, or a fault found during commissioning. Assume something will slip and build a fallback so the business keeps trading.
A 4G/5G mobile broadband router is a cheap insurance policy that can keep a small team online for days while a primary circuit is finalised. For larger sites, a dedicated backup connectivity line or SD-WAN setup can hold traffic automatically until the main link is ready.
Because most systems are now cloud-based, staff with laptops and mobile data can often work from home during any gap. Communicate the contingency to the team before the move so nobody is caught out.
Protect your data and security through the move
Moving hardware is a moment of heightened risk: kit gets handled by third parties, boxes go missing, and rushed reconfiguration can leave firewalls or Wi-Fi wide open. Confirm your backups are complete and verified before anything is unplugged, ideally with an off-site cloud backup solution so nothing depends on physical devices in transit.
Rebuild the network to a known-good configuration rather than plugging things back in loosely. The firewall, guest Wi-Fi separation and remote access should all be checked before staff connect. Treat the new site's network security as a fresh setup, not a copy-and-hope.
Keep an asset list of every device moved, and account for each one on arrival. If any equipment is lost or stolen in transit, you'll know immediately and can act — including remotely wiping company laptops or phones.
Test everything before the first working day
The goal is that staff arrive, sit down and work — nothing more dramatic. That only happens if the network, internet, Wi-Fi, phones, printers and access to cloud apps are all tested by someone before the team walks in.
Run a proper commissioning checklist: confirm the internet circuit throughput matches what you ordered, that failover actually fails over, that every desk outlet is live, that Wi-Fi covers the whole floor, and that a test call in and out of your phone system works. Print a simple test call, test email and test file-access routine and tick each item off.
Having your IT partner on-site for the first morning is worth it. Small teething issues are normal, and quick on-site IT support turns a stressful morning into a non-event.
Who should own the move?
An office relocation touches connectivity, telecoms, cabling, hardware and security at once — and each has its own supplier lead times. Left to individual departments, the pieces rarely line up. A single owner who holds the timeline and chases every dependency is the difference between a smooth move and a costly one.
For most SMEs, the most reliable approach is to run the relocation as a managed IT project delivery engagement, with one point of contact coordinating circuits, cabling, phones and the day-one cutover. If you're planning a move in the capital, our IT support London team can survey both sites and build the plan around your trading hours.
Whatever you decide, start early. The businesses that move without losing internet or phones are simply the ones that ordered their connectivity first and left nothing to chance.