Leased line pricing has fallen steadily for years, which means anyone three years into a contract is very likely overpaying — sometimes by half. What stops businesses switching isn't loyalty, it's fear of the gap: a day without internet costs more than a year of savings. The good news is that professionally-run migrations don't have a gap. The circuits overlap; the risk is engineered out.
Step 0: read your current contract before anything else
Two clauses decide your timeline: the minimum term end date, and the cancellation notice period — commonly 30 to 90 days, and often required in writing. Miss the notice window and many contracts auto-renew for another year at the old price.
Diary the notice date the moment you know it. The golden rule: order the new circuit first, serve notice only when the new line has a confirmed delivery date — never the other way round.
Why the new line goes in alongside the old one
A leased line install takes 30-90 working days and its own staged process. Running it in parallel with your existing service costs you a short period of double rental — typically one or two months — and buys you something priceless: a cutover you can rehearse and reverse.
During the overlap you soak-test the new circuit with real traffic: throughput both ways, latency, failover behaviour, VoIP quality at busy hour. Problems surface while the old line still carries the business.
The technical details that decide how smooth it feels
Plan these before cutover day and the day itself is an anticlimax:
- IP addressing: your public IPs belong to the old carrier and won't move — inventory everything pinned to them (DNS, VPNs, whitelists, mail SPF) and prepare the new values
- DNS: drop TTLs to 5 minutes a week before, so record changes propagate fast on the day
- Firewall: pre-build the new WAN configuration so cutover is a cable move and config swap, not live engineering
- VPNs and third parties: warn anyone who whitelists your IP — banks, suppliers, remote sites — with the date and new addresses
Cutover day, minute by minute
A rehearsed cutover takes under an hour, scheduled out of hours: move the WAN to the new circuit, update DNS, bring VPN tunnels up on the new IPs, then walk a test sheet — outbound browsing, inbound mail, card terminals, phones, site-to-site links, remote workers.
Keep the old circuit connected but idle for a defined fallback window — a week is comfortable. If anything critical misbehaves, moving back is minutes, not a crisis.
Then, and only then, cancel the old line
Once the new circuit has carried a full business week cleanly, serve or confirm cancellation on the old service per the contract's notice terms and get the end date in writing. Reconcile the final bill — early-termination or auto-renew charges are worth challenging if your notice was correctly served.
If this feels like a lot of moving parts: it is, and it's exactly what we do for clients end to end — get a switching quote and we'll manage the overlap, the cutover and the old provider's paperwork, including a look at whether your wider network should change at the same time.
